I expect there will be more of these, but in the interest of keeping everyone informed, Greg forwarded an email this morning with updates on the status of the historic Bridge:
From: talbot-avenue-bridge-events@googlegroups.com
Sent: Wednesday, June 5, 2019 1:12 AM
Subject: Talbot Avenue Bridge demolition beginsToday, a little after 7am, Talbot Avenue Bridge closed. By midday clamps had been attached to the girders and steel extensions, in preparation for later removal by crane. By the end of the day, the wood edging along either side of the Bridge had begun to be removed.
If you would like to view the demolition process, best viewing is on the 4th Avenue side of the Bridge (North Woodside).
The removal of the girders could happen soon, i.e within the next week and as soon as the end of this week. Purple Line continues, however, to wait for flaggers from CSX, without which this aspect of the demolition cannot proceed.